GLM Update: 21st October 2026

insurance claim, meetings

As agreed at the EGM, regular updates on the progress of the insurance claim and other matters relating to the running of the Mill will now be provided by Steve Hopkins in the owners’ section of the GLM website.

Insurance Claim

The insurers accepted liablility for the claim on 5th October 2026.

Alternative quotes are being obtained for a permanent repair to the roof – contractor visited on 13th October 2026.

Loss adjusters – Lorega – arranged for J P Bedford to project manage the reinstatement of the affected flats (who visited on 16th October).

The insurers continue to cover the costs of temporary accomodation, whilst longer term accomodation is sourced.

Directors’ Meeting – 5th October 2026

  • Letter from Johnsons sent on 6th October to all property owners regarding proactive management.
  • Decision taken to terminate contract with grounds contractor due to lack of consistency with works completed. (Johnsons formally terminated contract on 6th October).

Cleaners resigned on 6th October (due to a change of circumstances). New cleaners are being sourced by Johnsons.

Damage to car park barrier on 11th October – a quote is being obtained to repair.

Steve Hopkins – Director, GLM Management Company Ltd

Leave a comment